EPC Contract Template for England and Wales

Generate a bespoke document

What is a EPC Contract?

EPC Contracts are used in England and Wales for major energy, infrastructure and process plant projects, most often where project finance is involved and the lender requires single-point responsibility. The contractor carries design, procurement and construction risk for a fixed price and a fixed completion date, which is why these contracts are sometimes called turnkey contracts. They typically include performance testing, liquidated damages for delay and for underperformance, and a defects liability period after taking over.

Trusted by high-performance teams

Frequently Asked Questions

What is the difference between an EPC contract and a design and build contract?

Both place design and construction with one contractor, but an EPC contract usually goes further: a fixed price, a fixed completion date, and performance guarantees that the finished plant will achieve a stated output. Design and build is more common on buildings and often leaves performance risk with the employer.

Does the Construction Act apply to an EPC contract?

Yes, where the works are construction operations in the United Kingdom. Both parties gain the right to adjudicate at any time, and the statutory payment framework applies. Payment terms that do not comply are replaced by the Scheme for Construction Contracts, so drafting around them does not work.

What liquidated damages are usual in an EPC contract?

Two sets. Delay damages accrue per day or week of late completion, and performance damages apply if the plant fails to reach its guaranteed output. Both are normally capped, with an overall cap on total liability, and those caps are the contractor's real exposure.

Should an EPC contractor promise fitness for purpose?

It is a stricter standard than reasonable skill and care, and professional indemnity policies frequently exclude it. If the contract requires it, check that the insurance actually responds, or the promise has nothing behind it.

How do funders get protection under an EPC contract?

Usually through collateral warranties or a schedule of third party rights, with step-in rights allowing the funder to take over if the borrower defaults. The Contracts (Rights of Third Parties) Act 1999 is normally excluded so those rights are granted deliberately rather than by implication.

Reviewed by

Swetha Meenal

Legal Engineer, GenieAI

Swetha Meenal profile photo

A lawyer, legal researcher and legal tech founder, Swetha has built AI products deployed inside Tier 1 firms and enterprises. She ensures GenieAI's alignment with the latest regulation and executes testing on the legal robustness of Genie output.

Reviewed by

Imad Mohammed Nazar

Legal Engineer, GenieAI

Imad Mohammed Nazar profile photo

A Skadden-trained M&A lawyer, Imad advised on cross-border transactions and contractual risk before moving into legal AI. He reviews GenieAI's output for compliance and enforceability across our 150+ supported jurisdictions, as well as facilitating external benchmarking.

Jurisdiction

England and Wales

Publisher

GenieAI

Sector

Business

Cost

Free to use

Last updated

About the EPC Contract

An EPC Contract places design, procurement and construction of a project with a single contractor for an agreed price and completion date. Under England and Wales law it sits within the statutory construction contract regime, which means the payment and adjudication provisions of the Housing Grants, Construction and Regeneration Act 1996 apply whatever the contract itself says.

When do you need this document?

You need an EPC Contract when a project must be delivered to a fixed price and date with one party accountable for the whole outcome. That is typically a generating station, substation or grid connection, a process or manufacturing plant, a waste or water treatment facility, or a major infrastructure asset. It is the usual requirement where a project is funded on the strength of the asset itself, because a lender wants a single contractor carrying delay and performance risk rather than gaps between separate designers and builders.

What does it cover?

The contract fixes the scope through the employer's requirements and the contractor's proposals, and sets out the price and payment mechanism, the programme and completion date, and the testing the plant must pass before it is taken over. It allocates the risks that decide whether a project makes money: ground and site conditions, changes in law, delay caused by either party, and shortfalls in output. It then sets the consequences through liquidated damages for late completion and for underperformance, capped by an overall limit of liability, together with the defects liability period and the security package of bonds, parent company guarantees and insurance.

Common pitfalls

The most common problem is a mismatch between the design obligation and the insurance. A contract that promises the plant will be fit for a stated purpose imposes a stricter standard than reasonable skill and care, and professional indemnity policies frequently exclude it, leaving a promise with nothing behind it. The second is a liquidated damages regime that is not tied to the tests: if the performance tests are not defined precisely enough to produce a pass or fail, the damages become unenforceable in practice. The third is excluding the Contracts (Rights of Third Parties) Act 1999 without putting collateral warranties in place, which leaves funders and purchasers with no route to enforce anything.

GOVERNING LAW

Applicable law

This EPC Contract is drafted to comply with England and Wales law. Key legislation includes:

Housing Grants, Construction and Regeneration Act 1996: Applies to most construction contracts in the United Kingdom. It gives each party a right to refer disputes to adjudication at any time and imposes a statutory payment framework, so payment and dispute clauses that conflict with the Act will be overridden by the Scheme for Construction Contracts

Construction (Design and Management) Regulations 2015: Allocates health and safety duties between client, principal designer and principal contractor. An EPC Contract needs to state clearly which CDM role each party holds, because the duties apply regardless of what the contract says

Building Safety Act 2022: Introduces duty holder obligations and, for higher-risk buildings, gateway approvals and the golden thread of information. It also extends limitation periods for certain claims, which affects how long the contractor's exposure lasts

Contracts (Rights of Third Parties) Act 1999: Determines whether funders, purchasers and tenants can enforce contract terms directly. EPC Contracts usually exclude the Act and grant third party rights instead through collateral warranties or a schedule of third party rights

Supply of Goods and Services Act 1982: Implies terms as to reasonable skill and care in the design and services elements. Where the contract promises a specific performance outcome instead, that fitness for purpose obligation is a higher standard and should be a deliberate choice

Late Payment of Commercial Debts (Interest) Act 1998: Sets a statutory entitlement to interest on late payment unless the contract provides a substantial remedy. Interest rates well below the statutory rate can be challenged

Genie's Security Promise

Genie is the safest place to draft. Here's how we prioritise your privacy and security.

Your data is private:

We do not train on your data; Genie's AI improves independently

All data stored on Genie is private to your organisation

Your documents are protected:

Your documents are protected by ultra-secure 256-bit encryption

We are ISO27001 certified, so your data is secure

Organizational security:

You retain IP ownership of your documents and their information

You have full control over your data and who gets to see it