Skip to content

EPC Contract Template for England and Wales

Generate a bespoke document

On this page

What is a EPC Contract?

EPC Contracts are used in England and Wales for major energy, infrastructure and process plant projects, most often where project finance is involved and the lender requires single-point responsibility. The contractor carries design, procurement and construction risk for a fixed price and a fixed completion date, which is why these contracts are sometimes called turnkey contracts. They typically include performance testing, liquidated damages for delay and for underperformance, and a defects liability period after taking over.

About the EPC Contract

An EPC Contract places design, procurement and construction of a project with a single contractor for an agreed price and completion date. Under England and Wales law it sits within the statutory construction contract regime, which means the payment and adjudication provisions of the Housing Grants, Construction and Regeneration Act 1996 apply whatever the contract itself says.

When do you need this document?

You need an EPC Contract when a project must be delivered to a fixed price and date with one party accountable for the whole outcome. That is typically a generating station, substation or grid connection, a process or manufacturing plant, a waste or water treatment facility, or a major infrastructure asset. It is the usual requirement where a project is funded on the strength of the asset itself, because a lender wants a single contractor carrying delay and performance risk rather than gaps between separate designers and builders.

What does it cover?

The contract fixes the scope through the employer's requirements and the contractor's proposals, and sets out the price and payment mechanism, the programme and completion date, and the testing the plant must pass before it is taken over. It allocates the risks that decide whether a project makes money: ground and site conditions, changes in law, delay caused by either party, and shortfalls in output. It then sets the consequences through liquidated damages for late completion and for underperformance, capped by an overall limit of liability, together with the defects liability period and the security package of bonds, parent company guarantees and insurance.

Common pitfalls

The most common problem is a mismatch between the design obligation and the insurance. A contract that promises the plant will be fit for a stated purpose imposes a stricter standard than reasonable skill and care, and professional indemnity policies frequently exclude it, leaving a promise with nothing behind it. The second is a liquidated damages regime that is not tied to the tests: if the performance tests are not defined precisely enough to produce a pass or fail, the damages become unenforceable in practice. The third is excluding the Contracts (Rights of Third Parties) Act 1999 without putting collateral warranties in place, which leaves funders and purchasers with no route to enforce anything.

Governing law

Applicable law

This EPC Contract is drafted to comply with England and Wales law. Key legislation includes:

Swetha Meenal profile photo

Reviewed by

Swetha Meenal

Legal Engineer, GenieAI

A lawyer, legal researcher and legal tech founder, Swetha has built AI products deployed inside Tier 1 firms and enterprises. She ensures GenieAI's alignment with the latest regulation and executes testing on the legal robustness of Genie output.

LinkedIn
Imad Mohammed Nazar profile photo

Reviewed by

Imad Mohammed Nazar

Legal Engineer, GenieAI

A Skadden-trained M&A lawyer, Imad advised on cross-border transactions and contractual risk before moving into legal AI. He reviews GenieAI's output for compliance and enforceability across our 150+ supported jurisdictions, as well as facilitating external benchmarking.

LinkedIn

Frequently Asked Questions

What is the difference between an EPC contract and a design and build contract?

Both place design and construction with one contractor, but an EPC contract usually goes further: a fixed price, a fixed completion date, and performance guarantees that the finished plant will achieve a stated output. Design and build is more common on buildings and often leaves performance risk with the employer.

Does the Construction Act apply to an EPC contract?

Yes, where the works are construction operations in the United Kingdom. Both parties gain the right to adjudicate at any time, and the statutory payment framework applies. Payment terms that do not comply are replaced by the Scheme for Construction Contracts, so drafting around them does not work.

What liquidated damages are usual in an EPC contract?

Two sets. Delay damages accrue per day or week of late completion, and performance damages apply if the plant fails to reach its guaranteed output. Both are normally capped, with an overall cap on total liability, and those caps are the contractor's real exposure.

Should an EPC contractor promise fitness for purpose?

It is a stricter standard than reasonable skill and care, and professional indemnity policies frequently exclude it. If the contract requires it, check that the insurance actually responds, or the promise has nothing behind it.

How do funders get protection under an EPC contract?

Usually through collateral warranties or a schedule of third party rights, with step-in rights allowing the funder to take over if the borrower defaults. The Contracts (Rights of Third Parties) Act 1999 is normally excluded so those rights are granted deliberately rather than by implication.

Further Construction Agreement documents

Trusted by high-performance teams

Read customer stories
See moreShow fewer companies

Describe the task. Watch the team work.

Genie plans the work, builds the specialists and the tools it needs, then checks every stage.

Ready to agree with confidence?
See Genie in action.