FIDIC Red, Yellow and Silver Book: Which One You Are Being Asked to Sign

FIDIC Red Book vs Yellow Book vs Silver Book, the short answer

The three main FIDIC books differ by who carries design responsibility and how much risk the contractor takes. Under the Red Book the employer designs and the contractor builds to measurement. Under the Yellow Book the contractor designs and builds plant or works to the employer's requirements for a lump sum. Under the Silver Book the contractor takes on substantially the whole project risk, including most site information, in exchange for price and time certainty. Risk moves toward the contractor at each step: Red, then Yellow, then Silver.

FeatureRed BookYellow BookSilver Book
Full titleConditions of Contract for ConstructionConditions of Contract for Plant and Design-BuildConditions of Contract for EPC and Turnkey Projects
Who designsEmployerContractor, to employer's requirementsContractor, almost entirely
Pricing basisMeasurement against a bill of quantitiesLump sumLump sum, fixed
Contract administrationEngineerEngineerEmployer's Representative (no independent Engineer)
Unforeseen conditions riskMostly employerSharedMostly contractor
Typical useEmployer-designed building and civil worksProcess plant, power plant, design-build facilitiesPrivately financed, turnkey, lender-backed projects
Price and time certainty for employerLowerHigherHighest

If your business works on international infrastructure, or on UK projects with overseas funding or an international sponsor, you will eventually be handed a FIDIC contract. FIDIC, the International Federation of Consulting Engineers, publishes a suite of standard forms distinguished mostly by who carries design responsibility and how much risk sits with the contractor.

UK readers used to JCT and NEC will find the logic familiar but the vocabulary different. This is a practical guide to identifying which book you have been sent and what that means commercially.

The three books you are most likely to see

What is the FIDIC Red Book?

Conditions of Contract for Construction. The employer is responsible for the design, the contractor builds it, and the works are typically valued by measurement against a bill of quantities. An Engineer administers the contract, certifies payment and makes determinations. Choose this reading if the employer has provided a detailed and complete design. The Red Book suits traditional building and civil engineering work where the employer wants to control the design and accept the design risk that comes with it.

What is the FIDIC Yellow Book?

Conditions of Contract for Plant and Design-Build. The contractor designs and builds to the employer's requirements, usually for a lump sum. Design responsibility sits with the contractor, which matters for professional indemnity insurance and for any fitness for purpose obligation. The Engineer's role remains, and the works must pass the defined tests on completion before they are taken over. The Yellow Book is the common choice for process plant, power plant and mechanical or electrical facilities where performance against a specification is what the employer is buying.

What is the FIDIC Silver Book?

Conditions of Contract for EPC and Turnkey Projects. The contractor takes substantially more risk, including for much of the site information and for unforeseen conditions, in exchange for greater price and time certainty. There is no independent Engineer; the Employer's Representative administers directly on the employer's behalf. The Silver Book is commonly used where a project is privately financed and lenders want the contractor to deliver a complete, working facility for a fixed price by a fixed date. That single point of responsibility is the reason the contractor carries so much risk.

The suite also includes the Green Book for short contracts, the Gold Book for design, build and operate, the Emerald Book for underground works and the Pink Book harmonised for multilateral development bank funding. FIDIC first published the modern Red, Yellow and Silver forms as the 1999 first editions, and the 2017 second editions are the current mainstream reference. If you are comparing two documents, confirm which edition you hold, because the clause numbering and the risk positions changed between 1999 and 2017.

Why the book matters more than it looks

Moving from Red to Yellow to Silver shifts risk toward the contractor at each step, and the shift is significant rather than cosmetic. A business that prices a Silver Book job on Yellow Book assumptions has mispriced it. The three things to establish immediately are who owns the design, who carries the risk of unforeseen physical conditions, and who bears the consequences of errors in the employer's information. Under the Silver Book the contractor is generally taken to have verified the employer's data, so an error that would be the employer's problem under the Red Book becomes the contractor's problem here.

The Particular Conditions carry the real risk

This is the part UK readers will recognise from JCT. A FIDIC contract comes as General Conditions, which are the published standard text, plus Particular Conditions, which amend them for the specific project. Almost nobody uses the General Conditions unamended, and the Particular Conditions are where risk allocation is genuinely decided.

Reviewing a FIDIC contract therefore means reading the Particular Conditions against the General Conditions clause by clause, which is slow and error-prone by hand across a long document. This is the step where GenieAI does real work: it compares the amended document against the base form and surfaces every departure, then rates those departures red, amber or green against the positions your business has already agreed. The output is a shortlist of decisions rather than a re-read. The same clause-by-clause review process applies when you are handed any heavily amended standard form, including a service agreement for the works supporting a project.

Payment, performance and tests

How you get paid depends on the book. The Red Book pays against measurement, so the quantities actually carried out drive the valuation. The Yellow and Silver Books pay against a lump sum, usually released in milestone instalments as parts of the works are completed. Across all three, the contractor's performance is measured against a defined standard: the Yellow and Silver Books in particular tie takeover and final payment to tests on completion, and in many cases to a later performance test or performance guarantee for a power plant or process facility. Read the schedule of payments, the tests regime and any liquidated damages for delay or for a shortfall in performance together, because they interact.

Time bars deserve separate attention

FIDIC contracts contain notice requirements for claims, with a period running from when the contractor became aware or should have become aware of the event. Miss the window and the entitlement can be lost regardless of merit. UK practitioners are sometimes caught out because the equivalent provisions in JCT and NEC operate differently, and because enforceability of time bars varies by governing law.

Check the notice period, what starts it, and what the contract says happens if it is missed. Then make sure the people running the project actually know, because a claims notice provision only works if the site team is aware of it.

Dispute resolution

The 2017 editions provide for a Dispute Avoidance and Adjudication Board, with arbitration to follow if a dispute is not resolved. This is materially different from the UK position, where a statutory right to adjudicate at any time applies to most construction contracts under the Housing Grants, Construction and Regeneration Act 1996. On an international FIDIC project that statutory right will usually not be available, so the contractual machinery is what you have. Read it before you need it.

A short checklist for a business handed a FIDIC contract

  • Which book, and which edition (1999 first edition or 2017 second edition)
  • Who owns the design, and whether any fitness for purpose obligation sits with your insurance cover
  • Who carries unforeseen physical conditions risk, and who is treated as having verified the site data
  • How you are paid: measurement, lump sum or milestones, and what the tests on completion and performance tests require
  • Governing law and seat of arbitration, and whether any statutory adjudication right applies at all
  • Claim notice periods, and who on the project is responsible for serving them
  • Every departure in the Particular Conditions from the General Conditions, assessed against your own accepted positions

A Skadden-trained M&A lawyer, Imad advised on cross-border transactions and contractual risk before moving into legal AI. He reviews GenieAI's output for compliance and enforceability across our 150+ supported jurisdictions, as well as facilitating external benchmarking.

Interested in joining our team? Explore career opportunities with us and be a part of the future of Legal AI.

Share this post

Related content you might like

Show all

Podcast

Inside the Agentic Legal Specialist

"ChatGPT and Claude would do random on-the-spot work for you, which is not grounded in reality." Nitish Mutha, co-founder and CTO of GenieAI.

Podcast

Every Business Will Need a Trust Architect

Lord Wei thinks every business will need a new kind of role: a trust architect, the person who sets the rules its AI agents work within.

Podcast

How Legal Teams Really Buy AI Now

Legal teams have seen the flashy demo. Now they want AI that works on their own contracts, their own playbooks and their own rules.

Describe the task. Watch the team work.

Genie plans the work, builds the specialists and the tools it needs, then checks every stage.

Ready to agree with confidence?
See Genie in action.